The Bazaar Development Cycle |
3 |
============================ |
|
4 |
||
5 |
||
4439.1.4
by Martin Pool
Start cleaning up docs on bugs and release process |
6 |
Overview |
7 |
-------- |
|
8 |
||
9 |
Bazaar makes a release every four weeks, with one release candidate one |
|
10 |
week before the final release. We may vary this schedule from time to |
|
11 |
time, amongst other things to respond to bugs reported in the release |
|
12 |
candidate or the final release. Nevertheless, we value a regular release |
|
13 |
and we will normally slip only for serious bugs or regressions. |
|
14 |
||
15 |
See also: |
|
16 |
||
17 |
* `Bazaar Developer Document Catalog <index.html>`_ |
|
18 |
||
19 |
* `Releasing Bazaar <releasing.html>`_ -- the process for actually making |
|
20 |
a release or release candidate. |
|
21 |
||
22 |
Longer-Term Planning |
|
23 |
-------------------- |
|
24 |
||
25 |
Work spanning multiple releases is typically tracked in the bug tracker, |
|
26 |
and summarized in <http://bazaar-vcs.org/Roadmap>. |
|
27 |
||
28 |
||
29 |
General Process |
|
3778.2.1
by Martin Pool
Updated release process documentation. |
30 |
--------------- |
31 |
||
32 |
We normally have one person acting as the release manager, who |
|
33 |
organizes development for the release and also actually makes the release |
|
34 |
tarball and posts announcements. It can be a different person from one |
|
35 |
release to the next. |
|
36 |
||
37 |
Our usual process is that one week before release we will make a release |
|
38 |
branch from the trunk. We do one commit to that branch to change the |
|
39 |
version number to 'rc1', and advance the trunk version to 'dev' for the |
|
40 |
next release. |
|
41 |
||
42 |
We then publish and announce this release candidate according to the |
|
43 |
process below. We then have a week of general testing of the rc, |
|
44 |
including some time for plugin authors to update their code for any |
|
45 |
changes. |
|
46 |
||
47 |
Normally no changes will be made on the release branch unless serious bugs |
|
48 |
or regressions are found, and the release manager decides they should be |
|
49 |
merged in. After one week, the release branch's version number is updated |
|
50 |
and it's published as the final release. If regressions or serious |
|
51 |
problems are discovered after the final release we may make an additional |
|
52 |
point release from that branch. |
|
53 |
||
54 |
The process or timing can vary if that seems appropriate in a particular |
|
55 |
case but we try to release on a regular four week cycle. |
|
56 |
||
57 |
The net effect is that the code gets some extra testing before release, |
|
58 |
and the trunk is always open for general development. |
|
59 |
||
60 |
||
61 |
Starting a Release |
|
62 |
------------------ |
|
63 |
||
64 |
To start a new release cycle: |
|
65 |
||
66 |
#. Send mail to the list with the key dates, who will be the release |
|
67 |
manager, and the main themes or targetted bugs. Ask people to nominate |
|
68 |
objectives, or point out any high-risk things that are best done early, |
|
69 |
or that interact with other changes. |
|
70 |
||
71 |
#. Add a new "series" in Launchpad at <https://launchpad.net/bzr/+addseries>. |
|
72 |
There is one series for every *x.y* release. |
|
73 |
||
74 |
#. Add milestones to that series for the release candidate and the final |
|
75 |
release, and their expected dates. |
|
76 |
||
77 |
#. Deactivate old releases and their milestones. |
|
78 |
||
79 |
#. Update the version number in the ``bzr`` script, and the |
|
80 |
``bzrlib/__init__.py`` file. |
|
81 |
||
82 |
||
83 |
Weekly Metronome Mail |
|
84 |
--------------------- |
|
85 |
||
86 |
Every week the release manager should send a mail to the Bazaar list |
|
87 |
covering these points (as appropriate): |
|
88 |
||
89 |
* Early communication about changing dependencies or defaults |
|
90 |
||
91 |
* Reminder re lifecycle and where we're up to right now, in particular the |
|
92 |
dates for the next release and/or candidate. |
|
93 |
||
94 |
* Summary of recent successes and pending work. |
|
95 |
||
96 |
* Reminder re release objectives |
|
97 |
||
98 |
* Reminder re things needing attention, e.g. bug triage, reviews, testing |
|
99 |
of certain things, etc. |
|
100 |
||
101 |
||
102 |
Starting the release phase |
|
103 |
-------------------------- |
|
104 |
||
105 |
When it's time to make the release candidate: |
|
106 |
||
107 |
#. We create a new pqm-controlled branch for this release series. The |
|
108 |
branch must be created by Robert Collins on the pqm server. |
|
109 |
This branch means that from the first release candidate onwards, |
|
110 |
general development continues on the trunk, and only |
|
111 |
specifically-targetted fixes go into the release. |
|
112 |
||
113 |
#. Register the branch at <https://launchpad.net/products/bzr/+addbranch> |
|
114 |
||
115 |
#. The revision at the start of that branch is `released |
|
116 |
<releasing.html>`_ as the first RC. |
|
117 |
||
118 |
||
119 |
||
120 |
||
121 |
.. |
|
122 |
vim: filetype=rst textwidth=74 ai shiftwidth=4 |